Student Residence in Ndonjo Rinka

Ron Beaton send some good news on the work progress:
" Jitegemee Zaidi Construction have delivered 6000 ft of cut stone 6 X 6inches to site and 1200 ft 9 X 9 inch uncut stone. Also 120 tons of sand and 40 tons of Hardcore.
They have excavated foundations on one dormitory and placed the ring beam and intersection sub structure in place.

They have excavated the other dormitory site and have started laying the substructure ring beam of 9 X 9. The canteen site is marked out but as yet excavation not begun."